Grant PUD proposes rate increases, new charges for data centers

Grant County Public Utility District is proposing electricity rate increases for 2027 that would raise residential rates by about 3.1% and small-business rates by 3.6%, while establishing two new rate classifications for data centers and cryptocurrency operations.

With demand for electricity widely expected to climb, future rates are projected to grow 21% higher than next year’s proposed rate in nine years, according to a fact sheet published by the utility this week.

The proposal reflects the utility’s effort to accommodate growing industrial electricity demand without shifting the associated costs to residential customers, small businesses and agricultural users.

Under the proposal, residential electricity rates would increase from 6.5 cents per kilowatt-hour to 6.7 cents. For a household using 1,500 kilowatt-hours monthly, that translates to approximately $3 more per month, or $36 annually, in electricity consumption charges.

Small businesses would see rates rise from 5.5 cents to 5.7 cents per kilowatt-hour. A business consuming 5,000 kilowatt-hours monthly would pay approximately $120 more annually.

These calculations do not include fixed monthly charges.

Agricultural customers would also see increases. Irrigation rates would rise from 5.1 cents to 5.3 cents per kilowatt-hour, a 3.9% increase, while agricultural service rates would increase 4.4%.

Larger commercial and industrial customers face varying increases. Large general service rates would rise 9.5%, while industrial rates would increase 7.7%. Agricultural industrial customers would see a 10% increase, the largest percentage increase among existing customer classifications.

A significant feature of the proposal is the creation of two new classifications for electricity-intensive computing operations.

Grant PUD currently supplies electricity to eight data center operators in Grant County, which together accounted for approximately 37% of the county’s electricity consumption in 2025, according to figures released by the utility in August. The operations are concentrated around Quincy, where Microsoft, Sabey, Vantage and other companies operate large data center campuses.

The new High Density Compute classification, covering data centers and cryptocurrency operations, would carry a rate of 4.5 cents per kilowatt-hour in 2027. A separate Large High Density Compute classification for data centers would charge 4.8 cents.

Both would fall under the utility’s Tier 2 customer category, part of its strategy to ensure expanding industrial demand pays for the additional costs of supplying electricity.

Grant PUD calls the approach “Growth Pays for Growth.”

That distinction becomes more pronounced in the utility’s longer-term projections.

By 2036, residential rates are projected to reach 8.1 cents per kilowatt-hour, approximately 21% above the proposed 2027 rate. Small-business rates would reach 6.9 cents.

Rates for high-density computing operations, however, are projected to reach 8.3 cents, while large data centers could pay 9.4 cents per kilowatt-hour — nearly double their proposed initial rate.

Those figures are projections, not approved future rates.

Grant PUD identifies several challenges driving its rate planning, including growing industrial demand, transmission constraints, limits on hydropower production, carbon requirements and rising equipment costs.

The district says prices for power poles, transformers, wires and cables have nearly doubled over the past decade.

Despite the proposed increases, Grant PUD’s residential electricity rate would remain substantially below the Washington state average of 13.3 cents per kilowatt-hour cited in its proposal.

 

 